There are two task in my Microsoft Project File. Lets assume them as Task A and Task B. The first one here is takes around 90 days to complete while the second one takes around 66 days. Now the thing that I want to configure is that the second task must start after 21 days of Task A, and it must not end until the first one is over. I tried to work on dependencies but could found what I am looking for. The solution might be simple, but I am not able to work on it. I hope there will be some kind of solution that really works.