|
| |||||||||
| Tags: finishdate, lag, startdate |
![]() |
| | Thread Tools | Search this Thread |
|
#1
| |||
| |||
| Lag time between Start-Date and Finish-Date
Is it possible to add lag time between Start and Finish date of a single task? (I know its possibe to add lag time between 2 tasks that are linked) Thanks in advance. |
|
#2
| |||
| |||
| Re: Lag time between Start-Date and Finish-Date
Yes. It's called the Duration. Did you have something else in mind? Do you have an example? -- Trevor Rabey 0407213955 61 8 92727485 PERFECT PROJECT PLANNING www.perfectproject.com.au "Shahriar N k" <ShahriarNk@discussions.microsoft.com> wrote in message news:466CBC05-B484-4F2B-BED9-75FB8643A554@microsoft.com... > Is it possible to add lag time between Start and Finish date of a single > task? > (I know its possibe to add lag time between 2 tasks that are linked) > > Thanks in advance. |
|
#3
| |||
| |||
| Re: Lag time between Start-Date and Finish-Date
I will provide a little more clarification: Consider 1 single task T of Work = 8hrs, Resource = 100%, hence Duration = 8hrs. So, if T starts on 03/29 it will finish on 03/29. But i want T to finish on 03/30 with out affecting Work or Resource%. Do you think that is possible? Thanks. "Trevor Rabey - Perfect Project Planning" wrote: > Yes. It's called the Duration. > Did you have something else in mind? > Do you have an example? > -- > Trevor Rabey |
|
#4
| |||
| |||
| Re: Lag time between Start-Date and Finish-Date
Hi, Well, it's not easy, and I don't understand the relevance but yes, it is feasible Make the duration 2 days: work jumps to 16 hrs Task Usage View, change bottom tier of timescale to hours Enter 0 for work during the "interruption" hours until total work becomes the original 8 hrs. There you are. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Shahriar Nour Khondokar" <ShahriarNourKhondokar@discussions.microsoft.com> wrote in message news:C239C999-5D27-4C0C-A1A2-1975FA0EF602@microsoft.com... >I will provide a little more clarification: > Consider 1 single task T of Work = 8hrs, Resource = 100%, hence Duration = > 8hrs. > So, if T starts on 03/29 it will finish on 03/29. But i want T to finish > on > 03/30 with out affecting Work or Resource%. > Do you think that is possible? > Thanks. > "Trevor Rabey - Perfect Project Planning" wrote: > >> Yes. It's called the Duration. >> Did you have something else in mind? >> Do you have an example? >> -- >> Trevor Rabey > |
|
#5
| |||
| |||
| Re: Lag time between Start-Date and Finish-Date
Hi Shahriar , Welcome to this Microsoft Project newsgroup :) It sounds to me as if you want to split the task leaving a gap in between. Click the split button on the toolbar, move the cursor to the point you want to split the bar, then click and drag to the right. Alternatively, in the Task Usage view, enter zeros on the days you want the lag. FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP See http://tinyurl.com/2xbhc for my free Project Tutorials Shahriar N k wrote: > Is it possible to add lag time between Start and Finish date of a > single task? (I know its possibe to add lag time between 2 tasks that > are linked) > > Thanks in advance. |
|
#6
| |||
| |||
| Re: Lag time between Start-Date and Finish-Date
You can split the task using the "Spit Task" tool on the toolbar. That would be the equivalent to adding lag time since a split task begins and procedes for a period of time, then stands down with work stopping for a while, and then resumes so work can again procede. You can split the task as many times as you need. Note that when you do, the suration number doesnt change because time within the split is considered non-worknig time and so isn't counted in the duration. If you have a task that runs the first two weeks in February and split it by a week, the task will now finish 3 weeks after it starts however its duration will remain at 2 weeks. HTH -- Steve House [Project MVP] MS Project Trainer & Consultant Visit http://project.mvps.org/faqs.htm for the FAQs "Shahriar N k" <ShahriarNk@discussions.microsoft.com> wrote in message news:466CBC05-B484-4F2B-BED9-75FB8643A554@microsoft.com... > Is it possible to add lag time between Start and Finish date of a single > task? > (I know its possibe to add lag time between 2 tasks that are linked) > > Thanks in advance. |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "Lag time between Start-Date and Finish-Date" | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| error message: cant login This computer date/time is not synchornize with the date/time of network | fazalhassan | Networking & Security | 2 | 29-11-2011 09:29 AM |
| Baseline Column Date automatically updates Finish Date | Adam 1980 | Microsoft Project | 3 | 18-05-2011 07:08 PM |
| Remove Time from Start/Finish Date Columns When Exporting to Excel | Colleen | Microsoft Project | 2 | 15-04-2010 03:57 AM |
| MS Project 2003 Start/Finish Date Issue | mehunter48 | Windows Software | 0 | 14-09-2009 09:35 PM |
| Changing start date and creating formula for finish date | Lisa M | Microsoft Project | 2 | 11-09-2006 06:10 PM |