Go Back   TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project
Become a Member!
Forgot your username/password?
Register Tags Active Topics RSS Search Mark Forums Read SiteMap

Tags: , ,

Sponsored Links



Lag time between Start-Date and Finish-Date

Microsoft Project


Reply
 
Thread Tools Search this Thread
  #1  
Old 21-01-2009
Shahriar N k
 
Posts: n/a
Lag time between Start-Date and Finish-Date

Is it possible to add lag time between Start and Finish date of a single task?
(I know its possibe to add lag time between 2 tasks that are linked)

Thanks in advance.
Reply With Quote
  #2  
Old 21-01-2009
Trevor Rabey - Perfect Project Planning
 
Posts: n/a
Re: Lag time between Start-Date and Finish-Date

Yes. It's called the Duration.
Did you have something else in mind?
Do you have an example?
--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au

"Shahriar N k" <ShahriarNk@discussions.microsoft.com> wrote in message
news:466CBC05-B484-4F2B-BED9-75FB8643A554@microsoft.com...
> Is it possible to add lag time between Start and Finish date of a single
> task?
> (I know its possibe to add lag time between 2 tasks that are linked)
>
> Thanks in advance.



Reply With Quote
  #3  
Old 21-01-2009
Shahriar Nour Khondokar
 
Posts: n/a
Re: Lag time between Start-Date and Finish-Date

I will provide a little more clarification:
Consider 1 single task T of Work = 8hrs, Resource = 100%, hence Duration =
8hrs.
So, if T starts on 03/29 it will finish on 03/29. But i want T to finish on
03/30 with out affecting Work or Resource%.
Do you think that is possible?
Thanks.
"Trevor Rabey - Perfect Project Planning" wrote:

> Yes. It's called the Duration.
> Did you have something else in mind?
> Do you have an example?
> --
> Trevor Rabey


Reply With Quote
  #4  
Old 21-01-2009
Jan De Messemaeker
 
Posts: n/a
Re: Lag time between Start-Date and Finish-Date

Hi,

Well, it's not easy, and I don't understand the relevance but yes, it is
feasible
Make the duration 2 days: work jumps to 16 hrs
Task Usage View, change bottom tier of timescale to hours
Enter 0 for work during the "interruption" hours until total work becomes
the original 8 hrs.
There you are.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Shahriar Nour Khondokar" <ShahriarNourKhondokar@discussions.microsoft.com>
wrote in message news:C239C999-5D27-4C0C-A1A2-1975FA0EF602@microsoft.com...
>I will provide a little more clarification:
> Consider 1 single task T of Work = 8hrs, Resource = 100%, hence Duration =
> 8hrs.
> So, if T starts on 03/29 it will finish on 03/29. But i want T to finish
> on
> 03/30 with out affecting Work or Resource%.
> Do you think that is possible?
> Thanks.
> "Trevor Rabey - Perfect Project Planning" wrote:
>
>> Yes. It's called the Duration.
>> Did you have something else in mind?
>> Do you have an example?
>> --
>> Trevor Rabey

>



Reply With Quote
  #5  
Old 22-01-2009
Mike Glen
 
Posts: n/a
Re: Lag time between Start-Date and Finish-Date

Hi Shahriar ,

Welcome to this Microsoft Project newsgroup :)

It sounds to me as if you want to split the task leaving a gap in between.
Click the split button on the toolbar, move the cursor to the point you want
to split the bar, then click and drag to the right. Alternatively, in the
Task Usage view, enter zeros on the days you want the lag.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials


Shahriar N k wrote:
> Is it possible to add lag time between Start and Finish date of a
> single task? (I know its possibe to add lag time between 2 tasks that
> are linked)
>
> Thanks in advance.



Reply With Quote
  #6  
Old 22-01-2009
Steve House [MVP]
 
Posts: n/a
Re: Lag time between Start-Date and Finish-Date

You can split the task using the "Spit Task" tool on the toolbar. That
would be the equivalent to adding lag time since a split task begins and
procedes for a period of time, then stands down with work stopping for a
while, and then resumes so work can again procede. You can split the task
as many times as you need. Note that when you do, the suration number
doesnt change because time within the split is considered non-worknig time
and so isn't counted in the duration. If you have a task that runs the
first two weeks in February and split it by a week, the task will now finish
3 weeks after it starts however its duration will remain at 2 weeks.

HTH


--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://project.mvps.org/faqs.htm for the FAQs


"Shahriar N k" <ShahriarNk@discussions.microsoft.com> wrote in message
news:466CBC05-B484-4F2B-BED9-75FB8643A554@microsoft.com...
> Is it possible to add lag time between Start and Finish date of a single
> task?
> (I know its possibe to add lag time between 2 tasks that are linked)
>
> Thanks in advance.


Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project


Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "Lag time between Start-Date and Finish-Date"
Thread Thread Starter Forum Replies Last Post
error message: cant login This computer date/time is not synchornize with the date/time of network fazalhassan Networking & Security 2 29-11-2011 09:29 AM
Baseline Column Date automatically updates Finish Date Adam 1980 Microsoft Project 3 18-05-2011 07:08 PM
Remove Time from Start/Finish Date Columns When Exporting to Excel Colleen Microsoft Project 2 15-04-2010 03:57 AM
MS Project 2003 Start/Finish Date Issue mehunter48 Windows Software 0 14-09-2009 09:35 PM
Changing start date and creating formula for finish date Lisa M Microsoft Project 2 11-09-2006 06:10 PM


All times are GMT +5.5. The time now is 12:39 AM.