Hi B4plan,
Sorry for the delay in seeing your post. You might want to consider starting a new thread in the future versus adding onto a two year old thread.
To your question:
I created a simple project:
Four resources in two different groups
Assigned the resources to tasks
Display the Resource Usage view, add Percent Allocation to the timescaled (right side)
Group by - Resource Group
On the summary line I am seeing the correct data.
In the attached file, you'll see Resources assigned at 100% to tasks. The group summary line shows 50% allocation when I have one of the two resources assigned. When I have both resources assigned at 100%, the Percent Allocation at summary line shows 100%.
I am using Project 2007, SP 2