Updating Actual Work From Excel Timesheet Data

Microsoft Project


Reply
 
Thread Tools Search this Thread
  #1  
Old 11-01-2009
oisinirish
 
Posts: n/a
Updating Actual Work From Excel Timesheet Data

We use a very basic spreadsheet to produce weekly time sheet reports by
employee. Each employee's hours are entered daily and then associated with a
task code and cost code. Is it possible to import to project and therefore
update actual work?
Reply With Quote
  #2  
Old 11-01-2009
Jan De Messemaeker
 
Posts: n/a
Re: Updating Actual Work From Excel Timesheet Data

Hi,

Yes.
Most people write a VBA procedure to do that.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"oisinirish" <oisinirish@discussions.microsoft.com> wrote in message
news:39432C94-22E0-499E-B8FE-6C4F65DCD969@microsoft.com...
> We use a very basic spreadsheet to produce weekly time sheet reports by
> employee. Each employee's hours are entered daily and then associated with
> a
> task code and cost code. Is it possible to import to project and therefore
> update actual work?



Reply With Quote
  #3  
Old 19-01-2009
Prasanth
 
Posts: n/a
Re: Updating Actual Work From Excel Timesheet Data

Hi Jan,

Can you share the exact process of updating project plan from msexcel with
some sample,we have a requirement where in the client wants to pull the hours
from "Sage MAS500 eTimesheets" and populate them into the Project server so
that it shows Estimated and Actual hours worked on a project. The pull from
eTimesheets is in an excel format.

Also please update about possibilities of the same in project server 2003
and project server 2007

Regards,
Prasanth.

"Jan De Messemaeker" wrote:

> Hi,
>
> Yes.
> Most people write a VBA procedure to do that.
>
> --
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> +32 495 300 620
> For availability check:
> http://users.online.be/prom-ade/Calendar.pdf
> "oisinirish" <oisinirish@discussions.microsoft.com> wrote in message
> news:39432C94-22E0-499E-B8FE-6C4F65DCD969@microsoft.com...
> > We use a very basic spreadsheet to produce weekly time sheet reports by
> > employee. Each employee's hours are entered daily and then associated with
> > a
> > task code and cost code. Is it possible to import to project and therefore
> > update actual work?

>
>
>

Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project


Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "Updating Actual Work From Excel Timesheet Data"
Thread Thread Starter Forum Replies Last Post
MSP updates actual work when editing work in resource usage view sTu_Deimus Microsoft Project 6 11-05-2010 07:10 PM
Computer is reporting more data on C drive than actual Farrah Operating Systems 5 23-02-2010 05:52 AM
Can I put the Actual Date in Excel or VBA? Flaco Software Development 5 25-01-2010 08:09 PM
Work and Actual Work in the Resource Usage View Bobg Microsoft Project 4 02-11-2009 11:49 PM
automatic updating of data from excel to project Danny Microsoft Project 1 20-01-2008 12:23 AM


All times are GMT +5.5. The time now is 02:22 AM.