| Updating Actual Work From Excel Timesheet Data
We use a very basic spreadsheet to produce weekly time sheet reports by employee. Each employee's hours are entered daily and then associated with a task code and cost code. Is it possible to import to project and therefore update actual work? |
|
#2
| |||
| |||
| Re: Updating Actual Work From Excel Timesheet Data
Hi, Yes. Most people write a VBA procedure to do that. -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "oisinirish" <oisinirish@discussions.microsoft.com> wrote in message news:39432C94-22E0-499E-B8FE-6C4F65DCD969@microsoft.com... > We use a very basic spreadsheet to produce weekly time sheet reports by > employee. Each employee's hours are entered daily and then associated with > a > task code and cost code. Is it possible to import to project and therefore > update actual work? |
|
#3
| |||
| |||
| Re: Updating Actual Work From Excel Timesheet Data
Hi Jan, Can you share the exact process of updating project plan from msexcel with some sample,we have a requirement where in the client wants to pull the hours from "Sage MAS500 eTimesheets" and populate them into the Project server so that it shows Estimated and Actual hours worked on a project. The pull from eTimesheets is in an excel format. Also please update about possibilities of the same in project server 2003 and project server 2007 Regards, Prasanth. "Jan De Messemaeker" wrote: > Hi, > > Yes. > Most people write a VBA procedure to do that. > > -- > Jan De Messemaeker > Microsoft Project Most Valuable Professional > +32 495 300 620 > For availability check: > http://users.online.be/prom-ade/Calendar.pdf > "oisinirish" <oisinirish@discussions.microsoft.com> wrote in message > news:39432C94-22E0-499E-B8FE-6C4F65DCD969@microsoft.com... > > We use a very basic spreadsheet to produce weekly time sheet reports by > > employee. Each employee's hours are entered daily and then associated with > > a > > task code and cost code. Is it possible to import to project and therefore > > update actual work? > > > |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "Updating Actual Work From Excel Timesheet Data" | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| MSP updates actual work when editing work in resource usage view | sTu_Deimus | Microsoft Project | 6 | 11-05-2010 07:10 PM |
| Computer is reporting more data on C drive than actual | Farrah | Operating Systems | 5 | 23-02-2010 05:52 AM |
| Can I put the Actual Date in Excel or VBA? | Flaco | Software Development | 5 | 25-01-2010 08:09 PM |
| Work and Actual Work in the Resource Usage View | Bobg | Microsoft Project | 4 | 02-11-2009 11:49 PM |
| automatic updating of data from excel to project | Danny | Microsoft Project | 1 | 20-01-2008 12:23 AM |