|
| |||||||||
| Tags: fixed work, project 2002, schedule, tracking |
![]() |
| | Thread Tools | Search this Thread |
|
#1
| |||
| |||
| Tracking fixed work schedules
My first post ever on a forum... I would like to enter the hours spent per day per task for each resource, and have ms p calculate everything else while the work amount entered for each task remains constant. |
|
#2
| |||
| |||
| Re: Tracking fixed work schedules
Hi JPenny, If you have created your tasks and resources and assigned resource to tasks, Project has calculated the work as well as the number of hours of work per day per resource on the task. You can view the information in either the Task Usage view (organized by task) or the Resource Usage view (organized by resource.) You can also track Actual work in either view. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "JPenny" <JPenny.3kgubb@DoNotSpam.com> wrote in message news:JPenny.3kgubb@DoNotSpam.com... > > My first post ever on a forum... > > I would like to enter the hours spent per day per atsk or each > resourse, and have ms p calculate everything else while the work > amount > entered for the task remains constant. > > > -- > JPenny > ------------------------------------------------------------------------ > JPenny's Profile: http://forums.techarena.in/members/jpenny.htm > View this thread: > http://forums.techarena.in/microsoft...ct/1087992.htm > > http://forums.techarena.in > |
|
#3
| |||
| |||
| Re: Tracking fixed work schedules
I have tried to format those two views specifically to track my project, but when i enter something other than what project had projected, say 4 hours a day instead of 8, ms p changes "work" and not "duration". i found that if i clicked the resource and changed the "actual work" to something other than zero, then it will change the duration up to that amount, and not change "work". do i have to do this for every resource every day or week, before i enter it into the specific task to update the duration of the project? i was hoping there was a view i havent been able ot see yet that would let me enter the amount of time the resource worked on the a task, and automaticaly update the percent complete, durations, project finish dates, etc. |
|
#4
| |||
| |||
| Re: Tracking fixed work schedules
Hi JPenny, You should be supplying Actual Work when tracking. If you had a resource scheduled for 8 hours of work and enter 4 hours of Actual Work, Project will assume the remaining 4 hours still need to be done. What you want ... >a view i havent > been able ot see yet that would let me enter the amount of time > the > resource worked on the a task, and automaticaly update the percent > complete, durations, project finish dates, etc. is already there. Add Actual work to the right side(timescaled side) of the Task Usage view through Format > Details and Select "Actual Work". You can change the timescale through zooming in or out and enter Actual Work on a daily or weekly basis. Entering Actual Work will automatically update Remaining Work, Actual Cost, Actual and Remaining Duration, % Work complete, % Complete, Actual Start and Actual Finish. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "JPenny" <JPenny.3khdrb@DoNotSpam.com> wrote in message news:JPenny.3khdrb@DoNotSpam.com... > > I have tried to format those two views specifically to track my > project, > but when i enter something other than what project had projected, > say 4 > hours a day instead of 8, ms p changes "work" and not "duration". > i found that if i clicked the resource and changed the "actual > work" to > something other than zero, then it will change the duration up to > that > amount, and not change "work". do i have to do this for every > resource > every day or week, before i enter it into the specific task to > update > the duration of the project? i was hoping there was a view i > havent > been able ot see yet that would let me enter the amount of time > the > resource worked on the a task, and automaticaly update the percent > complete, durations, project finish dates, etc. > > > -- > JPenny > ------------------------------------------------------------------------ > JPenny's Profile: http://forums.techarena.in/members/jpenny.htm > View this thread: > Tracking fixed work schedules > > http://forums.techarena.in > |
|
#5
| |||
| |||
| Re: Tracking fixed work schedules
That was the ticet. I was close. thank you very much for givin me that little push over the edge. as i forge forward with the structuring, im sure ill run into more questions, but you really helped me get the ball rolling. It took me a while to find this forum. im really glad i did. |
|
#6
| |||
| |||
| Re: Tracking fixed work schedules
Super JPenny. Do post back in the future should you have any more questions. Glad to have helped and thanks for the feedback. Julie "JPenny" <JPenny.3kj2vb@DoNotSpam.com> wrote in message news:JPenny.3kj2vb@DoNotSpam.com... > > That was the ticet. I was close. thank you very much for givin > me that > little push over the edge. as i forge forward with the > structuring, im > sure ill run into more questions, but you really helped me get the > ball > rolling. It took me a while to find this forum. im really glad i > did. > > > -- > JPenny > ------------------------------------------------------------------------ > JPenny's Profile: http://forums.techarena.in/members/jpenny.htm > View this thread: > Tracking fixed work schedules > > http://forums.techarena.in > |
|
#7
| |||
| |||
| Re: Tracking fixed work schedules
Well Julie, ive been playin with my shecduling and now im not so sure i went about it the right way. i work on multiple projects with multiple resourses that dont spend all thier time on any one project or one task for any duration. but when i alocate my resourses to multiple task within a project, ms p makes them over alocated. what are my options when allocating resourse that may only be there for one day or more than one task per day? |
|
#8
| |||
| |||
| Re: Tracking fixed work schedules
Hi JPenny, Overallocation occurs either because you have a resource assigned at above his/her max. units to a single task, or more commonly because you have the resource assigned to multiple tasks which overlap in time. If you need the resource to work on multiple tasks simultaneously, you'll need to change the assignment units so the total assignment units on that day do not exceed the max. units for the resource. I suggest taking a read of Mike Glen's excellent series of articles/tutorials about Microsoft Project. You can find Mike's articles linked from: http://project.mvps.org/mike%27s_tutorials.htm Article 5 in particular addresses assignment of resources including overallocation explanations. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "JPenny" <JPenny.3kkxjb@DoNotSpam.com> wrote in message news:JPenny.3kkxjb@DoNotSpam.com... > > Well Julie, ive been playin with my shecduling and now im not so > sure i > went about it the right way. i work on multiple projects with > multiple > resourses that dont spend all thier time on any one project or one > task > for any duration. but when i alocate my resourses to multiple > task > within a project, ms p makes them over alocated. what are my > options > when allocating resourse that may only be there for one day or > more than > one task per day? > > > -- > JPenny > ------------------------------------------------------------------------ > JPenny's Profile: http://forums.techarena.in/members/jpenny.htm > View this thread: > Tracking fixed work schedules > > http://forums.techarena.in > |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "Tracking fixed work schedules" | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| How to configure task with fixed durration and fixed work? | BG_SAABer | Microsoft Project | 10 | 23-11-2009 03:23 PM |
| Fixed Duration vs Fixed Work | Lilly | Microsoft Project | 3 | 09-10-2009 10:12 PM |
| using MS Project for tasks tracking- not hours/effort or work tracking | Lisa@IMC | Microsoft Project | 9 | 22-07-2009 02:02 PM |
| Fixed Work Hours | userentry | Microsoft Project | 3 | 01-06-2009 09:18 PM |
| Fixed unit of work | Vijay | Microsoft Project | 3 | 07-12-2007 09:55 PM |