Originally Posted by
skier9er
I am transitioning to MS Project from Primavera. I lost all my screen shots of my Primavera filter setups and a list of what all they were. I am noticing MS Project filtering language/selections are a bit different than Primavera's. ie P3e = BL Start DD+30d: equals activities with BL Start on Data date and 30days after.
What filters setup do you run for 30/60/90 look ahead in ms project?
What other schedule reports using filtering do you run and can you send screen shots of the specific filters for Missed starts, missed finishes, late starts, late finishes, out of sequence tasks, actuals in the futures, negative slack and any other important ones I might be missing.
Thank you. Always a learning curve learning new software.