I have created few Tasks in MSP 2007 linked with finish to start. In this Task i manually set date to schedule from, hours per day set to 8 and Working Monday thru Friday. Going in details, the schedule shows Task 1 Duration 4 days, start Wed 6/2/10, Finish Mon 6/7/10 Task 2 Duration 3 days, start Mon 6/7/10, Finish Thu 6/10/10.
Here if you will notice instead of 6/7/10 Task2 should have a Start Date of 6/8/10, right? Any idea what went wrong behind this? Please help me to fix it.