I have a task which is estimated to take 300 hours for the completion and i have 3 resources assigned to the task. The very first resource starts immediately, the second resource starts in a week and the third resource starts in two weeks. For some reason the project is assigning 100 hours to each resource and is not assigning the task to complete the last resource. I have tried creating separate sub-tasks and have tried creating different resource to each sub-task and manually playing hours for each each resource in order to get the earliest resource to get completed but that's not working. Is there anyone who can help??