Scheduling multiple resources on a task to finish quicker

Microsoft Project


Reply
 
Thread Tools Search this Thread
  #1  
Old 09-12-2008
Member
 
Join Date: Sep 2004
Posts: 66
Scheduling multiple resources on a task to finish quicker

I have a task which is estimated to take 300 hours for the completion and i have 3 resources assigned to the task. The very first resource starts immediately, the second resource starts in a week and the third resource starts in two weeks. For some reason the project is assigning 100 hours to each resource and is not assigning the task to complete the last resource. I have tried creating separate sub-tasks and have tried creating different resource to each sub-task and manually playing hours for each each resource in order to get the earliest resource to get completed but that's not working. Is there anyone who can help??

Reply With Quote
  #2  
Old 09-12-2008
Member
 
Join Date: Sep 2005
Posts: 185
RE: Scheduling multiple resources on a task to finish quicker

It seems as if the project is recognizing the duration as manhours and not 300 hours. Just try going through the settings of the task and make sure that the "task
type" is set to fixed duration. I guess it might be set to "fixed work" and that's the reason Microsoft Project is recognizing tasks as 300 hours of work . You can even set the percentage of time the each resource will work on the task.
Reply With Quote
  #3  
Old 09-12-2008
Member
 
Join Date: Sep 2005
Posts: 179
I don't know how Microsoft Project calculation works but as far as i am aware you can input the work for each resource. In that way the task will end for all the resources on the same day. Just split the screen , use the form view for setting "Resource Schedule" and input following hours - 140, 100, 60 for your 3 resources and the task will end on the same day for all the 3 resources.
Reply With Quote
  #4  
Old 10-12-2008
Member
 
Join Date: Sep 2004
Posts: 66
RE: Scheduling multiple resources on a task to finish quicker

That worked, i tried splitting the task into three, assigned them separate resource to each subtask, entered hours accordingly for all of my 3 resources, added a deadline to the task and now the task are ending on the same day for all the 3 resources.
Reply With Quote
  #5  
Old 12-08-2009
Member
 
Join Date: Aug 2009
Posts: 4
Re: Scheduling multiple resources on a task to finish quicker

I also have a question...
Suppose A and B is working on the same project. On a particular date say for example 12/Aug/2009, A starts working on a task 'x' and B starts working on task 'y'. 'x' will take only 1.1 day but 'y' will take 2.2 days. After completing the task 'y' A has to join with B for doing task 'y'. So my problem is, when i am allocating some % (say for example 25 %) of "A"'s work for task 'y' , office project is showing over allocation on 12/Aug/2009. How will i rectify it. Please help me.
Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project
Tags: ,



Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "Scheduling multiple resources on a task to finish quicker"
Thread Thread Starter Forum Replies Last Post
Multiple resources available at different times for one task mjw Windows Software 1 02-11-2011 12:33 AM
Task Scheduling in JAVA Jagdish Gada Software Development 5 30-11-2009 08:45 AM
Task duration - start set by SF, finish set by FF. Can it be done & how ? ProjNoob Windows Software 3 12-08-2009 07:11 PM
Task Start & Finish dates Antonio00 Microsoft Project 6 17-03-2009 09:48 PM
Task scheduling : error 0x80070005: Access denied Fran├žois Miermont Windows Server Help 29 18-04-2005 05:59 PM


All times are GMT +5.5. The time now is 04:53 PM.