Hi, I am using MS project 2007. I’ve created a file with the following schedule: Software Acquisition, ERP Purchase Cost, ERP Annual Maintenance, BI Purchase Cost, BI Annual Maintenance, Consulting Services and Annual Support. In all above task, there is a fixed cost and a material resource linked. What I want to do is adding actual costs against these tasks in time phased manner.
The problem am facing is it is not allowing me to enter the actual costs manually in the timephased manner. Whenever I try adding the costs, Project automatically adds it against the total cost and does not reduce the remaining cost. Can someone here please let me know how can I add the cost in timephased manner as I would expect?
Thanks in advance.