As I understand it every task must have a predecessor. I understand the logic of this and why this is needed. However, how do i setup predecessors in the following situation.
Example:
Lets say that I am bulding a house and also furnishing it as an entire project.
Some of the tasks can be:
1. Build Foundation.
2. Put up Walls.
3. Roof
4. Plumming
5. Electrical
Now lets say that I want to start purchasing some furniture after the Roof goes up. The Predecessor for Furniture purchasing is the completion of the roof.
Now I want to start looking at the furniture 2 weeks after the roof goes up how do i indicate the furniture shopping must start 2 weeks after the roof goes on. Becuase if I don't do this then the project plan will look like the the roof shopping should start right after the roof goes on.
I hope I made my question as clear as possible.
Dane
Bookmarks