|
| ||||||||||
| Tags: microsoft project, project task |
![]() |
| | Thread Tools | Search this Thread |
|
#1
| ||||
| ||||
| Can I establish start and finish time for specific task?
|
|
#2
| ||||
| ||||
| Re: Can I establish start and finish time for specific task?
You can try to specify scheduling to the accuracy that you may require in MS Project by following the below methods:
|
|
#3
| ||||
| ||||
| RE: Can I establish start and finish time for specific task?
I dont think you will be able to do that. You have the option to set either a start or finish date but not both. Project normally calculates dates from data you enter about the work or duration required to complete each task. That will automatically set start and finish dates for all your tasks, except the start of the first task which should have a start date set if there is no predecessor. |
|
#4
| |||
| |||
|
I also have a question... Suppose A and B is working on the same project. On a particular date say for example 12/Aug/2009, A starts working on a task 'x' and B starts working on task 'y'. 'x' will take only 1.1 day but 'y' will take 2.2 days. After completing the task 'y' A has to join with B for doing task 'y'. So my problem is, when i am allocating some % (say for example 25 %) of "A"'s work for task 'y' , office project is showing over allocation on 12/Aug/2009. How will i rectify it. Please help me. |
|
#5
| |||
| |||
| Re: Can I establish start and finish time for specific task?
Hello, I am also trying to specify the start "time" of a task. I wholeheartedly agree that dates and times should be determined between tasks by the predecessor relationship and not "hardcoded". However, I mainly need to see the time on large project implementation plans. For ex, our last PSoft project implementation was 103 hours of 24/7 work so seeing the time really helped everyone stay on track. Anyway, I didn't see this thread until today and I had MS Project installed on my machine about two weeks ago. I am trying to find the 2010 equivalent of 2007's "Tools > Options > View" menu path and am a loss thus far. Can anyone help? I appreciate any info you can provide. |
|
#6
| |||
| |||
| Re: Can I establish start and finish time for specific task?
Hi ... nevermind, I just found it under File > Options > Date Format. thanks. |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "Can I establish start and finish time for specific task?" | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Looking for real world examples of using Start to Finish task relationships in MS Project | Emilk3 | Microsoft Project | 1 | 23-04-2011 07:00 PM |
| Remove Time from Start/Finish Date Columns When Exporting to Excel | Cic!cone | Microsoft Project | 2 | 15-04-2010 02:57 AM |
| How to remove/ignore the 'time' from the start/finish columns | Mannie | Windows Software | 1 | 12-02-2010 02:02 PM |
| Task duration - start set by SF, finish set by FF. Can it be done & how ? | ProjNoob | Windows Software | 3 | 12-08-2009 07:11 PM |
| Task Start & Finish dates | Antonio00 | Microsoft Project | 6 | 17-03-2009 09:48 PM |