Thread: Summary Task Duration incorrect

  1. #1
    Join Date
    Oct 2005
    Posts
    190

    Summary Task Duration incorrect

    I hope that some can answer for the question that I am having. I have a summary task duration which is not correct. For instance, I have got 2 subtasks that are Finish-to-Start, first one is 2 hours and second is 6 hours. The summary task tells a duration of 7 hours instead of 8 hours. I have tried to recalculate but that is not helping at all. Does anyone has any idea about same? Thanks.

  2. #2
    Join Date
    Sep 2005
    Posts
    1,434

    Re: Summary Task Duration incorrect

    Actually, the duration of a summary line is not defined by the duration of subtasks under it. The duration of a summary line is the difference in working time between the summary line start and finish. Those 2 dates are defined as the start date of the earliest subtask and the finish date of the latest subtask.

  3. #3
    Join Date
    Oct 2005
    Posts
    351

    Re: Summary Task Duration incorrect

    Can you tell us whether there is a lag between the finish of the first task and the start of the second? You can try to take a look at the time the tasks begin and end. Incase you are not showing time and date as well, then check Tools >> Options, View tab. Let us know what did you find.

  4. #4
    Join Date
    Oct 2005
    Posts
    190
    Between Tasks there is no lag, so that the sum of all durations should be the duration of the summary task. Actually, I have seen many examples where there is only one task, and I have included a summary line as well. The duration of the task is 2 hours and yet the summary for this task is only 1.5 hours? Thanks

Similar Threads

  1. Formula to count Detail Tasks within a Summary Task
    By blacksheep in forum Microsoft Project
    Replies: 3
    Last Post: 20-03-2012, 08:11 PM
  2. Incorrect end date for a task with the same duration
    By vsaddepalli in forum Microsoft Project
    Replies: 2
    Last Post: 14-12-2011, 10:15 PM
  3. Display baseline for Summary task
    By sa02000 in forum Microsoft Project
    Replies: 5
    Last Post: 25-10-2011, 08:04 PM
  4. incorrect duration calculation
    By J_R12 in forum Microsoft Project
    Replies: 2
    Last Post: 16-10-2011, 08:07 PM
  5. Project 2007 summary task duration help please?
    By KNLee in forum Windows Software
    Replies: 3
    Last Post: 24-04-2011, 02:03 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,948,959.47024 seconds with 17 queries