I hope that some can answer for the question that I am having. I have a summary task duration which is not correct. For instance, I have got 2 subtasks that are Finish-to-Start, first one is 2 hours and second is 6 hours. The summary task tells a duration of 7 hours instead of 8 hours. I have tried to recalculate but that is not helping at all. Does anyone has any idea about same? Thanks.