How to print time range on Gantt chart

Microsoft Project


Reply
 
Thread Tools Search this Thread
  #1  
Old 02-10-2008
Member
 
Join Date: Sep 2008
Posts: 3
How to print time range on Gantt chart

I am running MSP 2003 SP3. I want to print the time range of each task on the Gantt chart. It is a 5 day project with 1000 tasks, so it would be helpful to include both the start time and end time above the bar. I don't want the date as this would be too crowded.I have seen this before on a print out, but I can't see to figure out how to do it.Thanks.

Reply With Quote
  #2  
Old 03-10-2008
Member
 
Join Date: Nov 2005
Posts: 143
Re: How to print time range on Gantt chart

I dint understood your query properly. You want to format the timescale to show hours, is that you are trying to do ???
Reply With Quote
  #3  
Old 03-10-2008
Member
 
Join Date: Sep 2008
Posts: 3
No, I want to keep the Gantt chart in days. But I want to add a label to each task bar that includes the start and end time of each task, similar to adding the resource name label on the chart.I have seen this before, but cant figure out how to get it there.
Reply With Quote
  #4  
Old 03-10-2008
Member
 
Join Date: Nov 2005
Posts: 143
Re: How to print time range on Gantt chart

If you want to show the start time and complete the time according to the task above each bar on the Gantt chart , then you can try adding values to the bars. Go to Format > Bar Styles, select the bar and specify the field you might be willing to show. You can add [start] field or the [finish] field but then it will show up date and time. In order to show time part of the start and finish field you will have to create a custom field using formula. You can first add text field to the table and add formula via Tools > Customize > Fields. The below formula will help you for pulling date portion from the start and finish fields:

Format([Start],"hh:mm") & " to " & Format([Finish],"hh:mm")

You can now show the text field above the task bar via

Then show the text field above the task bar via Format > Bar Styles.
Reply With Quote
  #5  
Old 03-10-2008
Member
 
Join Date: Sep 2008
Posts: 3
You understood exactly what I wanted to do and your solution worked perfectly. Thanks so much!
Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project
Tags: , ,



Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "How to print time range on Gantt chart"
Thread Thread Starter Forum Replies Last Post
how to create a gantt chart from a pert chart ? Loeb Microsoft Project 5 08-07-2011 10:24 AM
Print out of GANTT Chart Project 2010 KOVID Microsoft Project 1 26-03-2010 03:43 PM
How to print a Gantt Chart view without table information? Leoniee Windows Software 5 19-03-2010 04:35 AM
How do I print just the task list without any Gantt chart EshiKaa Microsoft Project 2 04-05-2009 09:10 PM
Project 2003 - Print Gantt Chart BetweenTwo Dates CeeTee Microsoft Project 2 29-04-2009 07:53 PM


All times are GMT +5.5. The time now is 05:47 AM.