Move gantt chart to current task start date

Microsoft Project


Reply
 
Thread Tools Search this Thread
  #1  
Old 15-09-2008
Member
 
Join Date: Jul 2008
Posts: 6
Move gantt chart to current task start date

Can anyone help? I'm sure that its possible to move the Gantt chart to the currently selected task's start date. However I cant remember how. Any help appreciated.
Reply With Quote
  #2  
Old 15-09-2008
Gérard Ducouret
 
Posts: n/a
Re: Move gantt chart to current task start date

Hello,
Click the "Scroll to Task " button in the Standard tool bar : it's a
yellow-brown finger pointing on a blue bar.

Gérard Ducouret

"bmcqueen" <bmcqueen.3fsbnb@DoNotSpam.com> a écrit dans le message de news:
bmcqueen.3fsbnb@DoNotSpam.com...
>
> Can anyone help? I'm sure that its possible to move the Gantt chart to
> the currently selected task's start date. However I cant remember how.
> Any help appreciated.
>
>
> --
> bmcqueen
> ------------------------------------------------------------------------
> bmcqueen's Profile: http://forums.techarena.in/members/bmcqueen.htm
> View this thread: http://forums.techarena.in/microsoft...ct/1038464.htm
>
> http://forums.techarena.in
>



Reply With Quote
  #3  
Old 15-09-2008
Mike Glen
 
Posts: n/a
Re: Move gantt chart to current task start date

Hi bmcqueen ,

Welcome to this Microsoft Project newsgroup :)

On the Standard toolbar there's a small icon of a finger pointing on the
Gantt Chart. This is the Scroll to... task (goto) button - try that. Or
Edit/Go To... and fill in an ID or Date.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials


bmcqueen wrote:
> Can anyone help? I'm sure that its possible to move the Gantt chart to
> the currently selected task's start date. However I cant remember how.
> Any help appreciated.



Reply With Quote
  #4  
Old 15-09-2008
Member
 
Join Date: Jul 2008
Posts: 6
Thanks for your help. I thought that it would be obvious once it was pointed out to me!

Bill
Reply With Quote
  #5  
Old 16-09-2008
Mike Glen
 
Posts: n/a
Re: Move gantt chart to current task start date

You're welcome, Bill :-)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials

bmcqueen wrote:
> Thanks for your help. I thought that it would be obvious once it was
> pointed out to me!
>
> Bill



Reply With Quote
  #6  
Old 16-09-2008
Gérard Ducouret
 
Posts: n/a
Re: Move gantt chart to current task start date

You are welcome, Bill

Gérard

"bmcqueen" <bmcqueen.3fsh7b@DoNotSpam.com> a écrit dans le message de news:
bmcqueen.3fsh7b@DoNotSpam.com...
>
> Thanks for your help. I thought that it would be obvious once it was
> pointed out to me!
>
> Bill
>
>
> --
> bmcqueen
> ------------------------------------------------------------------------
> bmcqueen's Profile: http://forums.techarena.in/members/bmcqueen.htm
> View this thread: Move gantt chart to current task start date
>
> http://forums.techarena.in
>



Reply With Quote
  #7  
Old 16-09-2008
Member
 
Join Date: Jul 2008
Posts: 6
Hi Glen,

Just thought I'd check out your link for the free project tuturials but see that I'd need to join techtrax. Can you comment on the usefulness of techtrax for Project and other Mirosoft product resources?

regards,
Bill
Reply With Quote
  #8  
Old 16-09-2008
Mike Glen
 
Posts: n/a
Re: Move gantt chart to current task start date

Hi Bill,

Good question! TechTrax used to be completely free, but the owners decided
that there should be a small contribution for more advanced articles to
defray costs. However, as far as my articles on Project are concerned, the
first 28 are still free to view, as are other earlier articles on other
Microsoft topics (mainly the Office suite of programs). If you select the
Subscribe/Membership button it will take you to the subscription page where
there is the offer of free subscription (which mainly allows your email
address be known to TechTrax so that they can email you the latest articles
as they are published).

I would suggest you get the free subscription first, read through the
contents of several of the different offerings to see if you believe it
would be worth the $3 per month that is requested for full membership.
Unfortunately, the editor has had a multitude of personal traumers in her
family which have recently precluded monthly editions. You can read of her
problems in the editoral to the June edition.

As I wrote them, it's, perhaps, not fair to ask me if the Project articles
are worth reading. I've tried to keep them simple so that even a newcomer
to Project can have a real chance of understanding of how Project should be
made to work. Perhaps someone who has used the articles would provide more
unbiassed comment.

Mike Glen
Project MVP

bmcqueen wrote:
> Hi Glen,
>
> Just thought I'd check out your link for the free project tuturials
> but see that I'd need to join techtrax. Can you comment on the
> usefulness of techtrax for Project and other Mirosoft product
> resources?
>
> regards,
> Bill



Reply With Quote
  #9  
Old 17-09-2008
JulieS
 
Posts: n/a
Re: Move gantt chart to current task start date

"Mike Glen" wrote in message
news:%23XksUJBGJHA.4864@TK2MSFTNGP02.phx.gbl...
> Hi Bill,

<snip>
> As I wrote them, it's, perhaps, not fair to ask me if the Project
> articles are worth reading. I've tried to keep them simple so
> that even a newcomer to Project can have a real chance of
> understanding of how Project should be made to work. Perhaps
> someone who has used the articles would provide more unbiassed
> comment.
>
> Mike Glen
> Project MVP

<snip>

Bill,

As Mike won't sing the praises of his tutorials -- I will. I refer
many to Mike's articles both here in the newsgroups as well as when
I am teaching classes. They are well written and do a wonderful job
of demonstrating key concepts in using MS Project successfully. If
you are unsure of the subscription, read the first 28 articles for
free -- you'll get a wealth of knowledge in just those articles
alone.

Julie
Project MVP



Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project


Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "Move gantt chart to current task start date"
Thread Thread Starter Forum Replies Last Post
how to create a gantt chart from a pert chart ? Laurence Microsoft Project 5 08-07-2011 11:24 AM
Need Help, Task Start Date wrong player Microsoft Project 8 06-06-2011 06:51 PM
Gantt chart displaying past although tasks start later in future Erolp Microsoft Project 1 18-03-2011 04:38 AM
How do I print just the task list without any Gantt chart Larry Microsoft Project 2 04-05-2009 10:10 PM
Dependent start date task with fixed end date horatio123 Microsoft Project 1 31-08-2008 08:59 AM


All times are GMT +5.5. The time now is 12:20 AM.