| Tags: actual, capture, complete |
![]() |
| | Thread Tools | Search this Thread |
|
#1
| |||
| |||
| Capture Actual work when a task is complete Does anyone know how to do this? Example: A task has a duration of 5 days and 40 hours of work. The person doing the tasks spends 5 hrs on the task. We enter 5 in the actual work column and the % complete changes to 13%; which is correct. Then if they enter 100 into the %complete column the actual work changes to 40 hrs, which isn't true, it was 5 hours. How can I capture the real value? |
|
#2
| |||
| |||
| Re: Capture Actual work when a task is complete
Hello DWall, Add the remaining work field to your view. Enter 5 hours of actual work, set the remaining work to zero. The task will be 100% complete with a duration of .63 days. The most accurate and detailed method of entering actuals is using either the Task Usage or Resource Usage view. You can then enter when the actual work took place. So, in the instance that the task was 5 hours of work but spread across 5 days, entering the hour per day in either view will show the 5 days duration (zero duration variance) but 5 hours of actual work. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "DWall" <DWall.3cpwnc@DoNotSpam.com> wrote in message news:DWall.3cpwnc@DoNotSpam.com... > > I want to be able to capture the actual amount of work a task took > and > when I mark the task complete the actual amount of work entered > doesn't > get recalculated to match the planned work. > > Does anyone know how to do this? > > Example: > A task has a duration of 5 days and 40 hours of work. The person > doing the tasks spends 5 hrs on the task. We enter 5 in the actual > work > column and the % complete changes to 13%; which is correct. Then if > they enter 100 into the %complete column the actual work changes to > 40 > hrs, which isn't true, it was 5 hours. How can I capture the real > value? > > > -- > DWall > ------------------------------------------------------------------------ > DWall's Profile: http://forums.techarena.in/members/53185.htm > View this thread: > Capture Actual work when a task is complete > > http://forums.techarena.in > |
|
#3
| |||
| |||
| Re: Capture Actual work when a task is complete
% Complete is about Duration only, not Work or Cost nor even about the progress of the Task. The sequence in which you put the data in, and which data you put where, are crucial to getting your progress measurement right. There is some information left out of your example. What is the Status Date? What date did the Task actually start? Use the Tracking Gantt View and the Tracking Table, so you can see what you are doing when you input the data. Show the Tracking Toolbar (View, Toolbars) Avoid typing in % Complete or % Work Complete, ie don't do it. They will be calculated for you when you input the Actual and Remaining. Let's say that the 5 Day Task started as planned on Monday and the Status Date is the end of Monday. 8 Hours of Work was planned for that 1 day. 5 Hours was done and the Task is finished. Address Duration first (just as you did when you first planned the Task). In the Tracking Table, input the Actual Start Date (Monday), then input the Actual Duration (1 Day). Alternatively, select the Task and just click the "Update as scheduled" button on the Tracking Toolbar. MSP will assume that the Actual Start date was the planned start date and that the Task was worked on continuously up to the Status Date. Next input the Remaining Duration which in this case is 0 since the Task is finished. Next input the Actual Work which is 5 Hours. If the situation was slightly different, say the Status Date is the end of Wednesday and there was various numbers of Hours of Work, such as 5, 6 and 7 on Monday, Tuesday, Wednesday, and suppose the Remaining Duration is not 0, say 2 Days. You can use the Task Usage View to input the Actual Work for each day. Right click anywhere on the yellow grid to get a menu which allows you to show the Actual Work. Input 5, 6 and 7 for Monday, Tuesday, Wednesday. MSP pushes the unused part of the total Work (3+2+1 = 6 Hours) to the following Monday, extending the Duration by 1 Day, ie 1 day more than you think it will take. Just delete the Work from that day and the Remaining Duration goes back to 2 Days. Alternatively, return to the Tracking Gantt View and the Tracking Table and set Remaining Duration back to 2 Days. Next look at adjusting the Actual and Remaining Cost. By default, Actual Cost is calculated automatically from Duration and Work but you can disconnect it in Tools, Options, Calculation. Hope this helps. Trevor Rabey 0407213955 61 8 92727485 PERFECT PROJECT PLANNING www.perfectproject.com.au "DWall" <DWall.3cpwnc@DoNotSpam.com> wrote in message news:DWall.3cpwnc@DoNotSpam.com... > > I want to be able to capture the actual amount of work a task took and > when I mark the task complete the actual amount of work entered doesn't > get recalculated to match the planned work. > > Does anyone know how to do this? > > Example: > A task has a duration of 5 days and 40 hours of work. The person > doing the tasks spends 5 hrs on the task. We enter 5 in the actual work > column and the % complete changes to 13%; which is correct. Then if > they enter 100 into the %complete column the actual work changes to 40 > hrs, which isn't true, it was 5 hours. How can I capture the real > value? > > > -- > DWall > ------------------------------------------------------------------------ > DWall's Profile: http://forums.techarena.in/members/53185.htm > View this thread: Capture Actual work when a task is complete > > http://forums.techarena.in > |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "Capture Actual work when a task is complete" | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Work and Actual Work in the Resource Usage View | Bobg | Microsoft Project | 4 | 02-11-2009 10:49 PM |
| % complete ,% work complete and physical % complete | Amey | Microsoft Project | 4 | 01-11-2009 08:15 PM |
| Planned vs Actual Work and % complete | Hardip | Microsoft Project | 4 | 09-07-2009 06:28 AM |
| Duration vs. Actual Work | Glenn | Microsoft Project | 12 | 18-02-2009 02:09 AM |